Many people search for the meaning of BOQ when entering construction and contracting projects. The Bill of Quantities (BOQ) is a pivotal document in the lifecycle of any engineering project, but understanding its true role is closely tied to the type of contract and the project phase.
In this educational guide, we clarify the exact meaning of a BOQ, the difference between it, takeoff, and pricing, and the correct steps for its preparation.
Simply put, the Bill of Quantities (BOQ) is a document that translates engineering drawings and specifications into a list of organized items. Each item usually consists of:
For practical illustration, you can download an educational BOQ sample (CSV) to see the final shape of the table and how items are sequenced (quantities in the sample are hypothetical for explanation purposes).
To simplify the concepts:
A common mistake is considering the bill of quantities as a final and binding contractual document in all cases. In reality, the role of the BOQ is determined by the "contract type":
(Disclaimer: The mechanisms mentioned as general examples are based on standard contract models like FIDIC Red Book, Second Edition 2017, Clause 12, and the actual mechanism always depends on the contract conditions signed between the parties. These examples are not considered a general rule applicable to all projects).
Preparing the bill relies on the available drawings. In the Tendering phase, design drawings are used. For accurate takeoff before execution, it is preferable to use Shop Drawings.
The engineer calculates lengths, areas, and volumes. To ensure consistency of measurements across projects, it is recommended to rely on standard measurement rules such as the recent edition of NRM 2: Detailed measurement for building works (2nd Edition, October 2021) issued by the RICS. (Note: NRM 2 is an engineering standard to unify the language of measurement and avoid overlap, but it is not a legally binding document unless your specific project documents stipulate adherence to it).
The description must be clear, detailed enough, and linked to the projects technical specifications reference to avoid any misunderstanding during execution.
This is a step to audit the conformity between the bills and the drawings, ensuring items are not duplicated (e.g., calculating excavation work twice) or omitting necessary works that are not clearly drawn but are required from an engineering standpoint.